Deficient / Incomplete Services at Jamuna Apartments
(Please click on the title to see the post fully)
Project was supposed to be completed
by 2015 and all the services to be provided by 2015. However the project is
still not complete even after the delay of 5 years. Many Services remain
deficient/incomplete/absent till date. The Team JARWA (2020) has taken over the
maintenace activities without proper handing over/taking over and without ensuring
completion of the various facilties/installations. The project was approved by
the Govt. on the promise by the Jamuna Apartments of providing the various
services as per the following list:-
1 Installation
of UV (Ultra-Violet) System in the STP (Sewerage Treatment Plant) to kill
bacteria and disinfect the waste water.
2 Installation
of Solar Lighting System for common
lighting to reduce electricity bills.
3 Installation
of Organic Waste Converter for
converting the organic waste and garbage into bio-compost in order to reduce
pollution.
4 Energy Conservation Measures
5 Approval from the Forest Department (0.01457 hectares)
6 Thermal Insulation Coating on the roofs of the building to keep
the buildings cool during summer and warm during winter.
7 Monitoring of Air Quality, Soil
Quality, Ground Water and Noise
Level
8 Supply of treated water (90
KlD from STP) to the washrooms for
flushing
9 Rain Water Harvesting
10
First aid room
11
Water Connection from Municipality Kharar
12
Sewerage Connection from Municipality Kharar
13 Storm/Rain Water Control. Presently the colony gets flooded
just after 15 minutes of the rain.
Extracts of the Govt. Letter are
provided here for the information of all the residents.